[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100374,779,1,"单选题","(2018年真题)根据《标准施工合同》，监理人在施工准备阶段的职责是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按专用条款约定的时间向承包人无条件发出开工通知",false,{"key":16,"text":17,"correct":14},"B","在开工日期15日前向承包人发出开工通知",{"key":19,"text":20,"correct":21},"C","批准或要求修改承包人报送的施工进度计划",true,{"key":23,"text":24,"correct":14},"D","组织编制施工“合同进度计划”","监理人征得发包人同意后，应在开工日期7天前向承包人发出开工通知，合同工期自开工通知中载明的开工日起计算。 如果约定的开工已届至但发包人应完成的开工配合义务尚未完成（如现场移交延误），由于监理人不能按时发出开工通知，则要顺延合同工期并赔偿承包人的相应损失。 如果发包人开工前的配合工作已完成且约定的开工日期已届至，但承包人的开工准备还不满足开工条件，监理人仍应按时发出开工的指示，合同工期不予顺延。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]