[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100368,779,1,"单选题","(2018年真题)《标准施工合同》通用条款规定的“基准日期”是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标截止日",false,{"key":16,"text":17,"correct":14},"B","开标之日",{"key":19,"text":20,"correct":14},"C","中标通知书发出之日",{"key":22,"text":23,"correct":24},"D","投标截止日前28日",true,"（五）物价浮动的合同价格调整 1.基准日期：用来划分该日后由于政策法规的变化和市场物价浮动对合价价格影响的责任。 以投标截止日期前第28天定义为基准日，作为划分合同风险的时间点。（补充）",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]