[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100365,779,1,"单选题","(2017年真题)根据《标准施工合同》，监理人征得发包人同意后，应在开工日期（ ）天前向承包人发出开工通知。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","14",false,{"key":20,"text":21,"correct":18},"C","21",{"key":23,"text":24,"correct":18},"D","28","监理人征得发包人同意后，应在开工日期7天前向承包人发出开工通知，合同工期自开工通知中载明的开工日起计算。 如果约定的开工已届至但发包人应完成的开工配合义务尚未完成（如现场移交延误），由于监理人不能按时发出开工通知，则要顺延合同工期并赔偿承包人的相应损失。 如果发包人开工前的配合工作已完成且约定的开工日期已届至，但承包人的开工准备还不满足开工条件，监理人仍应按时发出开工的指示，合同工期不予顺延。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]