[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100359,779,1,"单选题","(2016年真题)为了明确划分由于政策法规变化或市场物价浮动对合同价格影响的责任，《标准施工合同》中的通用条款规定的基准日期是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标截止日前第14天",false,{"key":16,"text":17,"correct":18},"B","投标截止日前第28天",true,{"key":20,"text":21,"correct":14},"C","招标公告发布之日前14天",{"key":23,"text":24,"correct":14},"D","招标公告发布之日前28天","（五）物价浮动的合同价格调整 1.基准日期：用来划分该日后由于政策法规的变化和市场物价浮动对合价价格影响的责任。 以投标截止日期前第28天定义为基准日，作为划分合同风险的时间点。（补充）",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]