[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100349,779,1,"单选题","(2015年真题)根据《标准施工合同》，就图纸、通用合同条款和已标价的工程量清单而言，优先解释的顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已标价的工程量清单→通用合同条款→图纸",false,{"key":16,"text":17,"correct":14},"B","已标价的工程量清单→图纸→通用合同条款",{"key":19,"text":20,"correct":14},"C","通用合同条款→已标价的工程量清单→图纸",{"key":22,"text":23,"correct":24},"D","通用合同条款→图纸→已标价的工程量清单",true,"（二）合同文件的优先解释次序 组成合同的各文件中出现含义或内容的矛盾时，如果专用条款没有另行的约定，以上合同文件序号为优先解释顺序。* 合同条款中未明确由谁来解释文件之间的歧义的，但可以结合监理工程师职责中的规定，总监理工程师应与发包人和承包人进行协商，尽量达成一致。不能达成一致时，总监理工程师应认真研究后审慎确定。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]