[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100345,779,1,"单选题","(2015年真题)根据《标准施工合同》，“合同进度计划”是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人投标书内提交的进度计划",false,{"key":16,"text":17,"correct":14},"B","施工准备阶段承包人编制的进度计划",{"key":19,"text":20,"correct":21},"C","承包人按监理人指示修改后经监理人批准的进度计划",true,{"key":23,"text":24,"correct":14},"D","承包人按监理人指示修改后经发包人批准的进度计划","2.审查进度计划 监理人对承包人的施工组织设计中的进度计划审查，监理人审查后，应在专用条款约定的期限内，批复或提出修改意见，否则该进度计划视为已得到批准。经监理人批准的施工进度计划称为“合同进度计划”。 3.合同进度计划 合同进度计划是控制合同工程进度的依据，对承包人、发包人和监理人均有约束力，不仅要求承包人按计划施工，还要求发包人的材料供应、图纸发放等不应造成施工延误，以及监理人应按照计划进行协调管理。合同进度计划的另一重要作用是，施工进度受到非承包人责任原因的干扰后，判定是否应给承包人顺延合同工期的主要依据。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]