[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100336,779,1,"单选题","(2009年真题)按照施工合同示范文本规定，下列关于发包人供应的材料设备运至施工现场后（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应当由发包人保管",false,{"key":16,"text":17,"correct":18},"B","应当由承包人保管",true,{"key":20,"text":21,"correct":14},"C","应当由监理人保管",{"key":23,"text":24,"correct":14},"D","应当由材料供应商保管","（四）对发包人提供的材料和工程设备管理 发包人在到货7天前通知承包人。承包人会同监理人在约定的时间内，在交货地点共同进行验收。材料在验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。 发包人要求向承包人提前接货的物资，承包人不得拒绝，但发包人应承担承包人由此增加的保管费用。 材料有质量或延期交付问题，由发包人承担由此增加的费用和（或）工期延误，并向承包人支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]