[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100335,779,1,"单选题","关于竣工验收的表述中，不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以承包人提交竣工验收申请报告的日期为实际竣工日期，并在工程接收证书中写明",false,{"key":16,"text":17,"correct":14},"B","实际竣工日用以计算施工期限，与合同工期对照判定承包人是提前竣工还是延误竣工",{"key":19,"text":20,"correct":21},"C","发包人在收到承包人竣工验收申请报告56d后未进行验收，视为未通过验收",true,{"key":23,"text":24,"correct":14},"D","实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的情况除外","2020版教材P114-117 竣工验收合格，监理人应在收到竣工验收申请报告后的56d内，向承包人出具经发包人签认的工程接收证书。以承包人提交竣工验收申请报告的日期为实际竣工日期，并在工程接收证书中写明。实际竣工日用以计算施工期限，与合同工期对照判定承包人是提前竣工还是延误竣工。发包人在收到承包人竣工验收申请报告56d后未进行验收，视为验收合格。实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的情况除外。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]