[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100332,779,1,"单选题","根据《标准设计施工总承包合同》，工程实施中应给予承包人延长工期、增加费用并支付合理利润的情形是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","异常恶劣的气候条件",false,{"key":16,"text":17,"correct":14},"B","不可预见的物质条件",{"key":19,"text":20,"correct":21},"C","监理人的指示错误",true,{"key":23,"text":24,"correct":14},"D","发包人提供的材料提前交货","2020版教材P110-112 本题考核的是涉及承包人索赔的条款。根据《标准施工合同中应给承包人补偿的条款》，监理人的指示延误或错误指示可补偿内容为工期、费用和利润，选项A可补偿内容为工期，选项B可补偿内容为工期和费用，选项D可补偿的内容为费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]