[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100331,779,1,"单选题","承包人施工期从监理人发出的开工通知中写明的开工日起算，至工程接收证书中写明的实际竣工日止的时间称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工期",true,{"key":16,"text":17,"correct":18},"B","合同工期",false,{"key":20,"text":21,"correct":18},"C","缺陷责任期",{"key":23,"text":24,"correct":18},"D","保修期","2020版教材P99 本题考核的是施工期。承包人施工期从监理人发出的开工通知中写明的开工日起算，至工程接收证书中写明的实际竣工日止。以此期限与合同工期比较，判定是提前竣工还是延误竣工。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]