[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100330,779,1,"单选题","下列情况承包人只能索赔工期和费用的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人要求违法",false,{"key":16,"text":17,"correct":18},"B","不可预见物质条件",true,{"key":20,"text":21,"correct":14},"C","发包人要求提前交货",{"key":23,"text":24,"correct":14},"D","发包人原因指示的暂停施工","2020版教材P110-112 本题考查的是索赔管理。标准施工合同中涉及应给承包人补偿的条款标准施工合同通用条款中，可以给承包人补偿的条款如表6-2 所示。选项A，可以索赔工期、费用、利润；选项C，只能索赔费用；选项D可以索赔工期、费用、利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]