[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100329,779,1,"单选题","某工程项目，承包人于2013年5月1日提交了工程竣工报告，5月15日通过了工程师组织的工程预验收，5月25日发包人组织工程验收，5月28日监理人向承包人出具有经发包人签认的工程接收证书，承包人的竣工日期应确定为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5月1日",true,{"key":16,"text":17,"correct":18},"B","5月15日",false,{"key":20,"text":21,"correct":18},"C","5月25日",{"key":23,"text":24,"correct":18},"D","5月28日","2020版教材P114-117 竣工验收合格，监理人应在收到竣工验收申请报告后的56天内，向承包人出具经发包人签认的工程接收证书。以承包人提交竣工验收申请报告的日期为实际竣工日期，并在工程接收证书中写明。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]