[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100326,779,1,"单选题","下列关于变更管理的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接指示的变更属于必须实施的变更",false,{"key":16,"text":17,"correct":18},"B","承包人建议的变更可以以口头形式提交监理人",true,{"key":20,"text":21,"correct":14},"C","承包人提出的变更涉及建议变更和要求变更两类",{"key":23,"text":24,"correct":14},"D","与承包人协商后确定的变更属于可能发生的变更","2020版教材P108-110 本题考查的是变更管理。直接指示的变更属于必须实施的变更，如按照发包人的要求提高质量标准、设计错误需要进行的设计修改、协调施工中的交叉干扰等情况。此时不需征求承包人意见，监理人经过发包人同意后发出变更指示要求承包人完成变更工作。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]