[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100320":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100320,779,1,"单选题","采用设计施工总承包，工程竣工验收未能通过，经过承包人修正缺陷再次验收检验合格。这种情况下，计算承包人的实际竣工日期应为()的日期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人第一次提交竣工验收报告",false,{"key":16,"text":17,"correct":18},"B","承包人修改后再次提交竣工验收报告",true,{"key":20,"text":21,"correct":14},"C","最终验收合格",{"key":23,"text":24,"correct":14},"D","办理竣工验收手续","2020版教材P114-117 重新验收如果合格，则工程接收证书中注明的实际竣工日，应为承包人重新提交竣工验收报告的日期。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]