[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100317,779,1,"单选题","土方填筑工程的施工中，因连续降雨导致停工15天，其中6天的降雨强度超过专用条款约定的标准构成延长合同工期的条件，则需要承包人应承担的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","其中6天的不利气候条件风险",false,{"key":16,"text":17,"correct":18},"B","其余9天的不利气候条件风险",true,{"key":20,"text":21,"correct":14},"C","停工15天的工期延误",{"key":23,"text":24,"correct":14},"D","停工15天造成的费用损失","2020版教材P93-95 异常恶劣的气候条件属于发包人的责任，\"不利气候条件\"对施工的影响则属于承包人应承担的风险，因此应当根据项目所在地的气候特点，在专用条款中明确界定不利于施工的气候和异常恶劣的气候条件之间的界限。土方填筑工程的施工中，因连续降雨导致停工15天，其中6天的降雨强度超过专用条款约定的标准构成延长合同工期的条件，而其余9天的停工或施工效率降低的损失，属于承包人应承担的不利气候条件风险。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]