[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100303,779,1,"单选题","某施工合同履行过程中，因施工需要临时中断道路交通，发包人委托承包人办理申请批准手续。因工程所处路段交通流量大，全天中断交通的要求未获批准，承包人只能在夜间施工，则由此造成的承包人损失应由（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人赔偿，延误的工期顺延",true,{"key":16,"text":17,"correct":18},"B","发包人赔偿，延误的工期不予顺延",false,{"key":20,"text":21,"correct":18},"C","承包人承担，延误的工期顺延",{"key":23,"text":24,"correct":18},"D","承包人承担，延误的工期不予顺延","2020版教材P96-97 本题考查的是发包人的义务。发包人应根据合同工程的施工需要，负责办理取得出入施工场地的专用和临时道路的通行权，以及取得为工程建设所需修建场外设施的权利，并承担有关费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]