[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100302":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100302,779,1,"单选题","某施工合同履行过程中，承包人发现由于公路管理部门的责任，连接施工场地与国道之间的道路不符合招标文件中说明的条件，则承包人由此增加的费用应由（）承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","公路管理部门",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","承包人与发包人共同","2020版教材P96-97 本题考查的是发包人的义务。发包人应根据合同工程的施工需要，负责办理取得出入施工场地的专用和临时道路的通行权，以及取得为工程建设所需修建场外设施的权利，并承担有关费用，开通施工场地与城乡公共道路的通道，以及专用条款约定的施工场地内的主要交通干道。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]