[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100301":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100301,779,1,"单选题","根据《标准施工合同》，投保工程一切险的保险金额不足以赔偿实际损失时，永久工程损失的差额部分应由（ ）进行补偿。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","合同条款确定的该风险责任人",{"key":23,"text":24,"correct":18},"D","造价咨询机构","2020版教材P95-96 本题考查的是明确保险责任。标准施工合同要求在专用条款具体约定保险金不足以赔偿损失时，承包人和发包人应承担的责任。如永久工程损失的差额由发包人补偿，临时工程、施工设备等损失由承包人负责。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]