[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100300,779,1,"单选题","在分包合同中，异常恶劣的气候条件属于（）的责任。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","分包人","2020版教材P93-95 本题考查的是订立合同时需要明确的内容。气候条件对施工的影响是合同管理中一个比较复杂的问题，异常恶劣的气候条件属于发包人的责任，不利气候条件对施工的影响则属于承包人应承担的风险。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]