[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100297,779,1,"单选题","根据《标准施工合同》，关于暂估价的说法，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","暂估价是签约合同价的组成部分",false,{"key":16,"text":17,"correct":14},"B","该笔款项在合同履行阶段一定发生",{"key":19,"text":20,"correct":14},"C","暂估价的内容在投标时难以确定准确价格",{"key":22,"text":23,"correct":24},"D","暂估价的内容包括计日工",true,"2020版教材P104-107 本题考查的是工程款支付管理。“暂估价”指发包人在工程量清单中给出的，用于支付必然发生但暂时不能确定价格的材料、设备以及专业工程的金额。该笔款项属于签约合同价的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]