[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100296,779,1,"单选题","收到承包人共同检验的通知后，监理人既未发出变更检验时间的通知，又未按时参加，则下列行为中错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人应与承包人共同进行材料、设备的试验",false,{"key":16,"text":17,"correct":14},"B","承包人将记录送交监理人后可继续施工",{"key":19,"text":20,"correct":21},"C","此次检查或试验视为监理人不在场情况下进行",true,{"key":23,"text":24,"correct":14},"D","监理人应签字确认","2020版教材P102-104 本题考查的是施工质量管理。监理人应与承包人共同进行材料、设备的试验和工程隐蔽前的检验。收到承包人共同检验的通知后，监理人既未发出变更检验时间的通知，又未按时参加，承包人为了不延误施工可以单独进行检查和试验，将记录送交监理人后可继续施工。此次检查或试验视为监理人在场情况下进行，监理人应签字确认。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]