[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100295,779,1,"单选题","某基础工程施工过程中，承包人未通知监理人检查即自行隐蔽，后又遵照监理人的指示进行剥露检验。经与监理人共同检验，确认该隐蔽工程的施工质量满足合同要求。下列关于处理此事件的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","给承包人顺延工期并追加合同价款",false,{"key":16,"text":17,"correct":14},"B","给承包人顺延工期，但不追加合同价款",{"key":19,"text":20,"correct":14},"C","给承包人追加合同价款，但不顺延工期",{"key":22,"text":23,"correct":24},"D","工期延误和费用损失均由承包人承担",true,"2020版教材P102-104 本题考查的是施工质量管理。承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖，监理人有权指示承包人钻孔探测或揭开检查，由此增加的费用和(或)工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]