[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100294,779,1,"单选题","施工合同履行中，发包人另行发包的设备安装工程开始施工，合同中没有规定土建承包人有配合安装的义务。工程师为避免施工的交叉干扰发出暂停部分土建施工指示，导致土建承包人的损失，由( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人承担，批准顺延工期",true,{"key":16,"text":17,"correct":18},"B","承包人承担，工期不可顺延",false,{"key":20,"text":21,"correct":18},"C","承包人承担，可以顺延工期",{"key":23,"text":24,"correct":18},"D","发包人承担，不批准顺延工期","2020版教材P99-102 本题考查的是施工进度管理。暂停施工并不是承包人的原因引起的，因发包人原因导致的暂停施工;所以应当由发包人承担损失，工期顺延。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]