[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100292,779,1,"单选题","关于物价浮动的合同价格调整，下列说法不正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人应以基准日期前的市场价格编制工程报价",false,{"key":16,"text":17,"correct":14},"B","简明施工合同的规定合同履行期间不考虑市场价格变化调整合同价款",{"key":19,"text":20,"correct":14},"C","工期12个月以上的施工合同，由发包人和承包人共同分担市场价格变化的风险",{"key":22,"text":23,"correct":24},"D","公式法调价适用于工程量清单中按单价支付部分和总价支付部分合同价格的调整",true,"2020版教材P93-95 标准施工合同通用条款规定用公式法调价，但调整价格的方法仅适用于工程量清单中按单价支付部分的工程款，总价支付部分不考虑物价浮动对合同价格的调整。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]