[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100291,779,1,"单选题","下列关于物价浮动的合同价格调整说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","是否允许调整合同价格，要视合同工期的长短来决定",false,{"key":16,"text":17,"correct":18},"B","调整价格的方法可以适用于工程量清单中按总价支付的部分",true,{"key":20,"text":21,"correct":14},"C","标准施工合同通用条款规定用公式法调价",{"key":23,"text":24,"correct":14},"D","工期在12个月以内的简明施工合同不考虑市场价格变化调整合同价款","2020版教材P93-95 本题考查的是订立合同时需要明确的内容。标准施工合同通用条款规定用公式法调价，但调整价格的方法仅适用于工程量清单中按单价支付部分的工程款，总价支付部分不考虑物价浮动对合同价格的调整。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]