[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100285":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100285,779,1,"单选题","某施工合同履行时，因施工现场尚不具备开工条件，已进场的承包人不能按约定日期开工，则发包人（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应赔偿承包人的损失，相应顺延工期",true,{"key":16,"text":17,"correct":18},"B","应赔偿承包人的损失，但工期不予顺延",false,{"key":20,"text":21,"correct":18},"C","不赔偿承包人的损失，但相应顺延工期",{"key":23,"text":24,"correct":18},"D","不赔偿承包人的损失，工期不予顺延","2020版教材P98 本题考查的是开工通知。如果约定的开工已届至但发包人应完成的开工配合义务尚未完成（如现场移交延误），由于监理人不能按时发出开工通知，则要顺延合同工期并赔偿承包人的相应损失。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]