[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100282,779,1,"单选题","承包商按投标文件中承诺的数量和型号的施工机械投入到施工中。监理人发现承包商使用的机械影响了工程进度，要求承包商增加。根据《施工合同示范文本》，承包商对此指示（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可以拒绝执行",false,{"key":16,"text":17,"correct":14},"B","应当执行，但可获得费用补偿",{"key":19,"text":20,"correct":14},"C","应当执行，但可获得费用和利润的补偿",{"key":22,"text":23,"correct":24},"D","应当执行，不能获得补偿",true,"2020版教材P103 本题考查的是对承包人施工设备的控制。承包商使用的施工设备影响了工程进度或施工质量时，监理人有权要求承包商增加或更换施工设备，由此增加的费用和工期延误责任由承包商承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]