[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100276,779,1,"单选题","某工程项目施工中现场出现了图纸中未标明的地下障碍物，需要作清除处理。按照合同条款的约定，承包人应在索赔事件发生后28天内向工程师递交（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","索赔报告",false,{"key":16,"text":17,"correct":18},"B","索赔意向通知",true,{"key":20,"text":21,"correct":14},"C","索赔依据和资料",{"key":23,"text":24,"correct":14},"D","工期和费用索赔的具体要求","2020版教材P110 本题考查的是索赔程序。索赔事件发生后，承包人应在索赔事件发生后的28天内向工程师递交索赔意向通知，声明将对此事件提出索赔。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]