[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100272,779,1,"单选题","监理人收到承包人变更报价书后的（）天内，根据合同约定的估价原则，商定或确定变更价格。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","28","2020版教材P109 本题考查的是变更估价。监理人收到承包人变更报价书后的14天内，根据合同约定的估价原则，商定或确定变更价格。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]