[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100268,779,1,"单选题","在施工合同履行中，发包人按合同约定购买了玻璃，现场交货双方共同清点检验接收后交承包人的仓库保管员保管，当施工需要使用时发现部分玻璃丢失，则应由（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","保管员负责赔偿损失",false,{"key":16,"text":17,"correct":14},"B","发包人承担损失责任",{"key":19,"text":20,"correct":21},"C","承包人负责赔偿损失",true,{"key":23,"text":24,"correct":14},"D","发包人与承包人共同承担损失责任","2020版教材P103 （四）对发包人提供的材料和工程设备管理承包人应根据合同进度计划的安排，向监理人报送要求发包人交货的日期计划。发包人应按照监理人与合同双方当事人商定的交货日期，向承包人提交材料和工程设备，并在到货7天前通知承包人。承包人会同监理人在约定的时间内，在交货地点共同进行验收。发包人提供的材料和工程设备验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]