[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100266,779,1,"单选题","工程师审查承包商提交的施工组织设计和进度计划时，认为承包商使用的施工设备数量不够而不能保证工程进度，则工程师（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有权要求增加施工设备，增加的费用由业主承担",false,{"key":16,"text":17,"correct":14},"B","无权要求增加施工设备，但有权要求加快施工进度",{"key":19,"text":20,"correct":21},"C","有权要求增加施工设备，增加的费用由承包商承担",true,{"key":23,"text":24,"correct":14},"D","无权要求增加施工设备，也无权要求加快施工进度","2020版教材P103 （五）对承包人施工设备的控制承包人使用的施工设备不能满足合同进度计划或质量要求时，监理人有权要求承包人增加或更换施工设备，增加的费用和工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]