[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100262,779,1,"单选题","《建设工程施工合同（示范文本）》规定，监理人对承包人索赔的处理决定，在法律上的效力（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","是终局的，对发包人具有强制约束力",false,{"key":16,"text":17,"correct":14},"B","不是终局的，对发包人具有强制约束力",{"key":19,"text":20,"correct":14},"C","是终局的，仅对承包人具有强制约束力",{"key":22,"text":23,"correct":24},"D","不是终局的，对发包人和承包人均没有强制约束力",true,"2020版教材P111 本题考查的是索赔程序。监理人的处理决定不是终局性的，对发包人和承包人都不具有强制性和约束力。承包人对监理人的决定不满意，可以按合同中争议条款提交约定的仲裁机构仲裁或诉讼。 承包人接受索赔处理结果，发包人应在做出索赔处理结果答复后28天内完成赔付。承包人不接受索赔处理结果的，按合同争议解决。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]