[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100260,779,1,"单选题","某施工合同约定钢材由发包商供应，当钢材到货时发包人与监理工程师都没有通知承包人验收，供应商就把钢材卸货于施工现场，在使用前发现钢材数量不足，则损失由（）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","钢材供应商","2020版教材P103 发包人要求向承包人提前接货的物资，承包人不得拒绝，但发包人应承担承包人由此增加的保管费用。发包人提供的材料和工程设备的规格、数量或质量不符合合同要求，或由于发包人原因发生交货日期延误及交货地点变更等情况时，发包人应承担由此增加的费用和（或）工期延误，并向承包人支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]