[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100259,779,1,"单选题","发包人在收到承包人竣工验收申请报告（）天后未进行验收，视为验收合格。实际竣工日期以提交竣工验收申请报告的日期为准。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","28",{"key":22,"text":23,"correct":24},"D","56",true,"2020版教材P116 本题考查的是竣工验收。发包人在收到承包人竣工验收申请报告56天后未进行验收，视为验收合格。实际竣工日期以提交竣工验收申请报告的日期为准。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]