[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100258,779,1,"单选题","施工过程中发生变更，而合同中没有适用或类似工程的价格，应（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由监理人提出适当的变更价格，经发包人批准后执行",false,{"key":16,"text":17,"correct":14},"B","由承包人提出适当的变更价格，经监理人确认后执行",{"key":19,"text":20,"correct":14},"C","由发包人提出适当的变更价格，经承包人同意后执行",{"key":22,"text":23,"correct":24},"D","按照成本加利润原则，由监理人商定",true,"2020版教材P109 本题考查的是变更估价原则。 （1）已标价工程量清单中有适用于变更工作的子目，采用该子目的单价计算变更费用； （2）已标价工程量清单中无适用于变更工作的子目，但有类似子目，可在合理范围内参照类似子目的单价，由监理人商定或确定变更工作的单价； （3）已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]