[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100257,779,1,"单选题","某建设项目施工过程中，现场有甲、乙两个分别承包的施工单位同时进行施工。当甲受到乙施工干扰时，甲受到的损失应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向发包人索赔",true,{"key":16,"text":17,"correct":18},"B","向乙施工单位索赔",false,{"key":20,"text":21,"correct":18},"C","向监理单位索赔",{"key":23,"text":24,"correct":18},"D","自行承担","2020版教材P101 发包人暂停施工的责任，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。（2）发包人责任的暂停施工3）协调管理原因。同时在现场的两个承包人发生施工干扰，监理人从整体协调考虑，指示某一承包人暂停施工。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]