[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100253":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100253,779,1,"单选题","根据《标准施工合同》，关于“暂列金额”的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额未包括在签约合同价内",false,{"key":16,"text":17,"correct":14},"B","暂列金额不可以计日工方式支付",{"key":19,"text":20,"correct":21},"C","暂列金额可能全部使用或部分使用",true,{"key":23,"text":24,"correct":14},"D","暂列金额应按合同规定全部支付给承包人","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]