[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100252,779,1,"单选题","下列（）情形导致承包人原因未在约定的工期内竣工，后续支付时应采用原约定竣工日与实际支付日的两个价格指数中较低的一个作为支付计算的价格指数。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不可抗力",false,{"key":16,"text":17,"correct":14},"B","工程量增加",{"key":19,"text":20,"correct":21},"C","承包商基础施工超挖",true,{"key":23,"text":24,"correct":14},"D","设计变更","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]