[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100249,779,1,"单选题","对于必须实施的变更，监理人在指示变更时应当（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","征求承包人意见，经发包人同意后发出变更指示",false,{"key":16,"text":17,"correct":18},"B","不需征求承包人意见，经发包人同意后发出变更指示",true,{"key":20,"text":21,"correct":14},"C","征求承包人意见，可自行确定发出变更指示",{"key":23,"text":24,"correct":14},"D","不需征求承包人意见，可自行确定发出变更指示","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]