[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100246,779,1,"单选题","下列关于不利物质条件的说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不利物质条件属于承包人应承担的风险",false,{"key":16,"text":17,"correct":18},"B","承包人遇到不利物质条件时，应采取合理措施继续施工，并通知监理人",true,{"key":20,"text":21,"correct":14},"C","监理人没有发出指示，承包人因采取合理措施而增加的费用和工期延误，由承包人承担",{"key":23,"text":24,"correct":14},"D","不利物质条件包括不利气候条件","1、不利物质条件属于发包人应承担的风险，指承包人在施工场地遇到的不可预见的自然物质条件、非自然的物质障碍和污染物，包括地下和水文条件，但不包括气候条件。 2、承包人遇到不利物质条件时，应采取适应不利物质条件的合理措施继续施工，并通知监理人。 3、监理人应当及时发出指示，构成变更的，按变更对待。 4、监理人没有发出指示，承包人因采取合理措施而增加的费用和工期延误，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]