[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100242,779,1,"单选题","发生承包人违反合同规定的情况时，处理方法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人向承包人发出立即解除合同通知",false,{"key":16,"text":17,"correct":14},"B","发包人向承包人发出整改通知",{"key":19,"text":20,"correct":14},"C","发出整改通知28天后承包人仍不纠正，监理人可发出解除合同通知",{"key":22,"text":23,"correct":24},"D","违约导致的费用增加和（或）工期延误由承包人承担",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]