[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100235,779,1,"单选题","由于施工过程发现文物、古迹以及其他遗迹、化石、钱币或物品，导致工期延长和成本增加，则承包商有权索赔（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期.费用和利润",false,{"key":16,"text":17,"correct":18},"B","工期.费用，但不包括利润",true,{"key":20,"text":21,"correct":14},"C","工期，但不包括费用",{"key":23,"text":24,"correct":14},"D","费用，但不包括工期","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]