[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100232,779,1,"单选题","施工工程竣工验收合格后，当事人对实际竣工日期有争议，则承包人的竣工日为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提交竣工验收申请报告日",false,{"key":16,"text":17,"correct":14},"B","开始进行竣工验收日",{"key":19,"text":20,"correct":21},"C","竣工验收合格日",true,{"key":23,"text":24,"correct":14},"D","签发工程接收证书日","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]