[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100231,779,1,"单选题","建设工程未经竣工验收，发包人擅自使用，后又组织竣工验收合格的，该工程竣工日期应为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","提交竣工验收申请报告日",false,{"key":16,"text":17,"correct":14},"B","竣工验收合格日",{"key":19,"text":20,"correct":14},"C","签发工程接收证书日",{"key":22,"text":23,"correct":24},"D","转移占有建设工程日",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]