[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100230,779,1,"单选题","某工程竣工验收阶段，承包人于 4 月 6 日向监理人递交了竣工验收申请报告，监理人4 月 8 日收到报告后，经审查于 4 月 20 日认为具备竣工验收条件，并于 4 月 26 日提请发包人竣工验收，但发包人延误竣工验收，则承包人的实际竣工日应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4月6日",true,{"key":16,"text":17,"correct":18},"B","4月8日",false,{"key":20,"text":21,"correct":18},"C","4月20日",{"key":23,"text":24,"correct":18},"D","4月26日","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]