[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100228,779,1,"单选题","当事人对建设工程实际竣工日期有争议时，对竣工日期的确定不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程经竣工验收合格的，以提交竣工验收报告日为竣工日期",false,{"key":16,"text":17,"correct":18},"B","建设工程经竣工验收不合格的，以重新竣工验收合格之日为竣工日期",true,{"key":20,"text":21,"correct":14},"C","发包人拖延验收的，以提交竣工验收报告日为竣工日期",{"key":23,"text":24,"correct":14},"D","建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]