[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100227,779,1,"单选题","某工程未经竣工验收，发包人于 4 月 6 日开始擅自使用工程，承包人于 4 月 15 日向监理人送交了竣工验收申请报告，4 月 20 日经验收质量合格，监理人于 4 月 25 日签发工程接收证书。当事人对工程实际竣工日期产生争议，则承包人的竣工日应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4月6日",true,{"key":16,"text":17,"correct":18},"B","4月15日",false,{"key":20,"text":21,"correct":18},"C","4月20日",{"key":23,"text":24,"correct":18},"D","4月25日","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]