[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100226,779,1,"单选题","《标准施工合同》中的“合同工期”是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人完成工程从开工之日起至实际竣工日经历的期限",false,{"key":16,"text":17,"correct":14},"B","合同协议书中写明的施工总日历天数",{"key":19,"text":20,"correct":14},"C","承包人从监理人发出的开工通知中写明的开工日起，至工程接收证书中写明的实际竣工日止的期限",{"key":22,"text":23,"correct":24},"D","承包人在投标函内承诺完成工程的时间期限，以及按照合同条款通过变更和索赔程序应给予的顺延工期时间之和",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]