[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100224":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100224,779,1,"单选题","根据《标准施工合同》，发包人在收到承包人竣工验收申请报告56天后未进行验收，视为验收合格。实际竣工日期为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收申请报告之日",true,{"key":16,"text":17,"correct":18},"B","承包人提交竣工验收申请报告后第28天",false,{"key":20,"text":21,"correct":18},"C","承包人提交竣工验收申请报告后第56天",{"key":23,"text":24,"correct":18},"D","工程接收证书颁发日","本题考查的是竣工验收管理。发包人在收到承包人竣工验收申请报告56天后未进行验收，视为验收合格。实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的情况除外。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]