[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100221,779,1,"单选题","如果施工索赔事件的影响持续存在，承包商应在该项索赔事件影响结束后的28日内向工程师提交（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","索赔意向通知",false,{"key":16,"text":17,"correct":18},"B","索赔通知",true,{"key":20,"text":21,"correct":14},"C","施工现场的记录",{"key":23,"text":24,"correct":14},"D","索赔依据","本题考查的是索赔管理。对于具有持续影响的索赔事件，在该项索赔事件影响结束后的28天内，承包人应向监理人递交最终索赔通知书。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]